Immigration / Serco
Fire Rectification, Melbourne Immigration Transit Accommodation
After a fire at Melbourne Immigration Transit Accommodation, DICE Contracting reinstated the affected accommodation wing for Serco in under four weeks so the site could re-occupy the area.
ClientSerco
Value$110k
CompletedSeptember 2022
LocationMelbourne, Victoria
SectorImmigration
Scope of works
- Repainting of common areas and fire-affected rooms
- HVAC replacement
- Replacement of furniture, fixtures and equipment
- Electrostatic spraying of beds
The constraint
An unplanned incident that took accommodation capacity offline at a facility that could not simply house people elsewhere.
Outcome
The wing was reinstated and re-occupied in under four weeks, which is the clearest demonstration we have of how fast DICE mobilises on emergency remediation.